MTH 601 (Math) Assignment solution Fall 2020
Hi Dear! Today we talk about MTH 601. Today we will only look at the question and the answer will be uploaded shortly time. If you know their answer, you must give your opinion in the comments.MTH 601 Assignment no 1 Solution file 2020. So Please support me on Social Networks.
MTH 610 Assignment Sopultion Fall 2020
- To solve this assignment, you should have good command over 01 - 09 lectures.
- Try to get the concepts, consolidate your concepts and ideas from these questions which you learn in the 01 to 09 lectures.
- Upload assignments properly through LMS, No Assignment will be accepted through email.
- Write your ID on the top of your solution file.
- Don’t use colorful backgrounds in your solution files.
- Use Math Type or Equation Editor etc. for mathematical symbols.
- You should remember that if we found the solution files of some students are the same then we will reward zero marks to all those students.
- Try to make a solution by yourself and protect your work from other students, otherwise, you and the student who send the same solution file will be given zero marks.
- Also, remember that you are supposed to submit your assignment in MS Word file format any other like scan images, etc. will not be accepted and we will give zero marks corresponding to these assignments.
- Earliest Start Time (EST)
- Earliest Finish Time (EFT)
- Latest Start Time (LST)
- Latest Finish Time (LFT)
- Calculate the total float for each activity.
- Identify the critical path.
- Find the project completion time.
MTH 601 ASSIGNMENT SOLUTION Fall 2020
Construct a table that shows the relationship between the activities and their predecessors.
Solution :
Active |
Predecessors |
Time(Duration) |
A |
- |
3 |
B |
A |
4 |
C |
A |
5 |
D |
A |
2 |
E |
B |
3 |
F |
C.D |
6 |
G |
D |
4 |
H |
B |
8 |
I |
E.F.G |
3 |
J |
G |
2 |
2. Calculate the following time estimates for each activity.
- Earliest
Start Time (EST)
- Earliest
Finish Time (EFT)
- Latest
Start Time (LST)
- Latest Finish Time (LFT)
3. Calculate the
total float for each activity.
Activities |
EST |
EFT |
LST |
LFT |
Total Float LST-EST |
A |
0 |
3 |
0 |
3 |
0 |
B |
3 |
7 |
10 |
14 |
7 |
C |
3 |
8 |
3 |
8 |
0 |
D |
3 |
5 |
6 |
8 |
3 |
E |
7 |
10 |
11 |
14 |
4 |
F |
8 |
14 |
8 |
14 |
0 |
G |
5 |
9 |
8 |
12 |
3 |
H |
17 |
15 |
6 |
14 |
1 |
I |
14 |
17 |
14 |
17 |
0 |
- Identify the critical path.
Possibiltes
|
Paths
|
Time(days) |
A-B-H |
1-2-3-8 |
3+4+8=
15 |
A-B-E-I |
1-3-7-8 |
3+4+3+3
= 13 |
A-C-F-I |
1-2-5-7-8 |
3+5+6+3
= 17 |
A-D-G-J |
1-2-4-6 |
3+2+4+2
= 11 |
5. Find the project completion time.
Project Completion time = 17 days
So Guys I hope you understand Assignment MTH 601 Solution fall 2020. Please support me on social Network Like, Youtube, Facebook.MTH 601 solutions 100% correct .